the outage affected 10.3 million users

He pause today, Monday around 14:29, had repercussions on 10.3 million users of various colonies, municipalities and mayors of different states of the country, assured Federal Electricity Commission (CFE).

The fault was caused by various power plants electricity they stopped working and this caused the energy to be sent to the transmission system, which stopped receiving another 7,500 megawatts.

although National Center for Energy Controla (Cenace) said the outage started at 14:28, CFE said: “at 14:29, 10.3 million users went out of service due to a low frequency throughout the country, this due to outages generation plants ”.


Read also: At least 5 other states report outages

The reactivation of the service started at 14:52, which according to CFE “is subject to the instructions of @CenaceMexico, which must guarantee the security of the national electricity system”.

But Prices He said that “at 14:45 (central time) there was a 60% recovery of cargo (representing 4,500 megawatts” in the National Interconnected System, prioritizing strategic areas. “

Read also: Explanation of the cause of the interruption: imbalance in the national interconnected system

By 15:55 CFE and Cenace reported that they had already recovered 94% of the load, ie 7,050 megawatts. Shortly afterwards, at 16:12, a 100% recovery was reported.